Productivity Improvement – click on the project breakdown diagram below for a detailed analysis
Objectives
Through our detailed planning, we determined the following key milestones:
- Confirm schedule, budget, and savings targets by week 10
- Dispatch all finished goods from consolidated location by week 19
- Manufacture all non-nut products from consolidated location by week 23
- Manufacture all nut products from consolidated location by week 32
Approach and results:
The Grant Thornton Productivity Improvement team made improvements to confirm schedules, budget and savings by:
- Establishing a steering committee comprised of eight client-led teams and assign objectives/targets
- Finalizing demolition and construction details, equipment layouts, and warehouse layouts
- Negotiating and finalizing all contracts for work performed by trades and subtrades
- Confirming ability to obtain permits from city council
Improvements were made in order to dispatch all finished goods from a consolidated location by:
- Negotiating a new fleet of lift trucks operable in a Very Narrow Aisle (VNA) application
- Completing implementation of Warehouse Management System
- Disassembling and re-erecting racking to VNA specifications
- Installing new docking equipment and loading safety devices
Manufacturing all non-nut products from a consolidated location was achieved by:
- Removing and relocating 10 packaging machines
- Modifying drainage, HVAC, and utility feeds for equipment
- Installing hand wash stations and necessary allergen controls to meet food safety standards
- Ensuring smooth employee transitions with new lunchroom and bathroom facilities
Manufacturing all nut products from consolidated location was achieved by:
- Removing and relocating three fryers with supporting infrastructure and two oil storage tanks
- Removing and relocating six packaging machines
- Designing and installing a new waste water handling system
- Installing a chiller unit for nut raw material cooling